A project costs €25 000 today and returns €6 500 at the end of each year for 6 years. The required rate of return is 12%. Find the profitability index PI.
NPV & IRR worksheet with answers
A project costs €25 000 today and returns €11 000 at the end of each year for 3 years. The required rate of return is 12%. Find the profitability index PI.
An investment of €60 000 gives these cash flows at the end of years 1 to 4: €16 000, €26 000, €18 000, €23 000. The cost of capital is 6%. Find the net present value NPV.
An investment of €60 000 gives these cash flows at the end of years 1 to 4: €26 000, €16 000, €25 000, €28 000. The cost of capital is 8%. Find the net present value NPV.
A project costs €10 000 and returns €7 000, €7 500, €5 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
An investment of €25 000 returns €8 500 at the end of each year for 5 years. Find its internal rate of return IRR in percent.
Answer key
- 1. PI = 1.069
- 2. PI = 1.057
- 3. NPV = 11566 €
- 4. NPV = 18218 €
- 5. IRR = 46.69 %
- 6. IRR = 20.76 %
Full step-by-step solutions: practise this topic on examproblems.com.