A machine is expected to save €18 000, €6 000, €10 000, €15 000 at the end of years 1 to 4, after which it is worthless. The required return is 9%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €50 000 today and returns €16 500 at the end of each year for 5 years. The required rate of return is 15%. Find the net present value NPV.
A project costs €60 000 today and returns €21 500 at the end of each year for 4 years. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €250 000 today. It generates €23 000 at the end of the first year, and the cash flow then grows by 3% per year forever. The cost of capital is 10%. Find the net present value NPV.
A project costs €40 000 and returns €12 000, €21 000, €21 000, €17 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.
A project costs €10 000 and returns €7 500, €6 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. PV = 39912 €
- 2. NPV = 5311 €
- 3. DPB = 3.612 years
- 4. NPV = 78571 €
- 5. MIRR = 20.46 %
- 6. IRR = 23.56 %
Full step-by-step solutions: practise this topic on examproblems.com.