A project costs €50 000 today and returns €15 000 at the end of each year for 5 years. The required rate of return is 12%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €4 000 at the end of each year for 5 years. The required rate of return is 10%. Find the net present value NPV.
A project costs €60 000 today and returns €23 000, €18 500, €12 000, €22 500, €24 500, €15 000 at the end of years 1 to 6. The cost of capital is 6%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A machine costs €50 000 today. It generates €6 500 at the end of each year for 8 years and can then be sold for €7 500. The cost of capital is 10%. Find the net present value NPV.
A project costs €40 000 and returns €19 000, €28 500, €17 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
An investment of €40 000 returns €12 500 at the end of each year for 4 years. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 4072 €
- 2. NPV = 5163 €
- 3. DPB = 3.66 years
- 4. NPV = −11824 €
- 5. IRR = 28.6 %
- 6. IRR = 9.564 %
Full step-by-step solutions: practise this topic on examproblems.com.