A project costs €40 000 today and returns €22 500 at the end of each year for 3 years. The required rate of return is 12%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €13 500, €9 500, €8 500, €11 500 at the end of years 1 to 4. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
A machine costs €50 000 today, lasts 6 years and costs €1 000 per year to run (paid at the end of each year). The cost of capital is 8%. Find its equivalent annual cost EAC.
An investment of €45 000 gives these cash flows at the end of years 1 to 3: €12 000, €17 000, €14 000. The cost of capital is 9%. Find the net present value NPV.
Project A costs €20 000 and returns €11 000, €8 000, €4 000 at the end of years 1 to 3. Project B costs €22 000 and returns €5 500, €8 500, €11 500. Find the crossover rate r* at which both projects have the same NPV, in percent.
A project costs €10 000 and returns €5 500, €5 500, €5 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 14041 €
- 2. PB = 3.739 years
- 3. EAC = 11816 €
- 4. NPV = −8872 €
- 5. r* = 2.969 %
- 6. IRR = 28.27 %