A project costs €25 000 today and returns €10 500 at the end of each year for 3 years. The required rate of return is 9%. Find the net present value NPV.
NPV & IRR worksheet with answers
A machine is expected to save €10 000, €15 000, €25 000, €15 000 at the end of years 1 to 4, after which it is worthless. The required return is 8%. What is the most the company should pay for the machine today? Find PV.
A project costs €40 000 today and returns €11 500 at the end of each year for 6 years. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €50 000 today and returns €16 000 at the end of each year for 5 years. The cost of capital is 10%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €50 000 and returns €36 500, €26 500, €29 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
An investment of €20 000 returns €6 000 at the end of each year for 4 years. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 1579 €
- 2. PV = 52991 €
- 3. DPB = 3.918 years
- 4. DPB = 3.934 years
- 5. IRR = 40.57 %
- 6. IRR = 7.714 %