A project costs €50 000 today and returns €20 000 at the end of each year for 5 years. The required rate of return is 15%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €25 000 today and returns €11 000 at the end of each year for 4 years. The required rate of return is 7.000000000000001%. Find the net present value NPV.
A machine costs €20 000 today, lasts 5 years and costs €2 000 per year to run (paid at the end of each year). The cost of capital is 10%. Find its equivalent annual cost EAC.
An investment of €75 000 gives these cash flows at the end of years 1 to 4: €35 000, €26 000, €20 000, €29 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.
A project costs €50 000 and returns €28 000, €29 000, €19 500, €17 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.
A project costs €25 000 and returns €16 500, €11 500, €18 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 17043 €
- 2. NPV = 12259 €
- 3. EAC = 7276 €
- 4. NPV = 18870 €
- 5. MIRR = 23.16 %
- 6. IRR = 37.52 %