A project costs €40 000 today and returns €16 500 at the end of each year for 4 years. The required rate of return is 15%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €20 000 today and returns €9 000 at the end of each year for 3 years. The required rate of return is 10%. Find the net present value NPV.
An investment of €60 000 gives these cash flows at the end of years 1 to 4: €17 000, €15 000, €20 000, €19 000. The cost of capital is 9%. Find the net present value NPV.
An investment of €60 000 gives these cash flows at the end of years 1 to 3: €18 000, €28 000, €18 000. The cost of capital is 6%. Find the net present value NPV.
A project costs €50 000 and returns €21 000, €33 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
A project costs €25 000 and returns €12 500, €13 000, €12 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 7107 €
- 2. NPV = 2382 €
- 3. NPV = −2875 €
- 4. NPV = −2986 €
- 5. IRR = 5.504 %
- 6. IRR = 23.54 %
Full step-by-step solutions: practise this topic on examproblems.com.