A project costs €50 000 today and returns €16 500 at the end of each year for 5 years. The required rate of return is 10%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €80 000 today and returns €29 000 at the end of each year for 5 years. The required rate of return is 12%. Find the net present value NPV.
A machine costs €50 000 today, lasts 7 years and costs €5 000 per year to run (paid at the end of each year). The cost of capital is 8%. Find its equivalent annual cost EAC.
An investment of €45 000 gives these cash flows at the end of years 1 to 3: €13 000, €20 000, €11 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €100 000 today. Its cash flow is €12 000 at the end of year 1 and grows by 4% per year until the last cash flow at the end of year 9. The cost of capital is 8%. Find the net present value NPV.
A project costs €50 000 and returns €23 500, €31 000, €25 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 12548 €
- 2. NPV = 24539 €
- 3. EAC = 14604 €
- 4. NPV = −11340 €
- 5. NPV = −13603 €
- 6. IRR = 27.23 %
Full step-by-step solutions: practise this topic on examproblems.com.