A machine is expected to save €5 000, €8 000, €18 000 at the end of years 1 to 3, after which it is worthless. The required return is 15%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €50 000 today and returns €15 500 at the end of each year for 4 years. The required rate of return is 5%. Find the profitability index PI.
A machine costs €30 000 today, lasts 5 years and costs €5 000 per year to run (paid at the end of each year). The cost of capital is 5%. Find its equivalent annual cost EAC.
A machine costs €40 000 today. It generates €10 500 at the end of each year for 5 years and can then be sold for €6 000. The cost of capital is 10%. Find the net present value NPV.
A project costs €10 000 and returns €7 000, €7 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
A project costs €25 000 and returns €13 000, €17 000, €13 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. PV = 22232 €
- 2. PI = 1.099
- 3. EAC = 11929 €
- 4. NPV = 3529 €
- 5. IRR = 25.69 %
- 6. IRR = 33.36 %