A project costs €80 000 today and returns €39 000 at the end of each year for 3 years. The required rate of return is 15%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €4 500 at the end of each year for 4 years. The required rate of return is 9%. Find the net present value NPV.
A project costs €50 000 today and returns €12 500 at the end of each year for 6 years. The cost of capital is 10%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €20 000 gives these cash flows at the end of years 1 to 4: €8 000, €6 000, €9 000, €5 000. The cost of capital is 9%. Find the net present value NPV.
A project costs €10 000 and returns €5 500, €7 000, €4 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €40 000 and returns €18 000, €15 000, €18 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 9046 €
- 2. NPV = 4579 €
- 3. DPB = 5.371 years
- 4. NPV = 2881 €
- 5. IRR = 33.04 %
- 6. IRR = 13.22 %