A project costs €100 000 today and returns €38 000 at the end of each year for 4 years. The required rate of return is 6%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €100 000 today and returns €27 000, €35 000, €25 500, €21 000, €37 500, €16 500 at the end of years 1 to 6. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
An investment of €60 000 gives these cash flows at the end of years 1 to 4: €21 000, €27 000, €14 000, €27 000. The cost of capital is 5%. Find the net present value NPV.
An investment of €20 000 gives these cash flows at the end of years 1 to 3: €5 000, €9 000, €7 000. The cost of capital is 12%. Find the net present value NPV.
A project costs €25 000 and returns €18 500, €10 500, €14 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €10 000 and returns €7 000, €6 000, €5 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 31674 €
- 2. PB = 3.595 years
- 3. NPV = 18796 €
- 4. NPV = −3379 €
- 5. IRR = 35.5 %
- 6. IRR = 39.03 %