A machine is expected to save €8 000, €5 000, €10 000, €6 000 at the end of years 1 to 4, after which it is worthless. The required return is 9%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €80 000 today and returns €39 000 at the end of each year for 3 years. The required rate of return is 12%. Find the net present value NPV.
A project costs €500 000 today. It generates €28 000 at the end of the first year, and the cash flow then grows by 2% per year forever. The cost of capital is 9%. Find the net present value NPV.
A machine costs €100 000 today. It generates €20 500 at the end of each year for 6 years and can then be sold for €20 000. The cost of capital is 8%. Find the net present value NPV.
A project costs €200 000 today. Its cash flow is €24 500 at the end of year 1 and grows by 4% per year until the last cash flow at the end of year 9. The cost of capital is 8%. Find the net present value NPV.
A project costs €20 000 and returns €8 000, €13 000, €9 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. PV = 23520 €
- 2. NPV = 13671 €
- 3. NPV = −100000 €
- 4. NPV = 7372 €
- 5. NPV = −23606 €
- 6. IRR = 22.79 %