A machine is expected to save €25 000, €15 000, €6 000 at the end of years 1 to 3, after which it is worthless. The required return is 6%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €100 000 today and returns €56 000 at the end of each year for 3 years. The required rate of return is 12%. Find the net present value NPV.
A machine costs €100 000 today. It generates €18 500 at the end of each year for 7 years and can then be sold for €20 000. The cost of capital is 8%. Find the net present value NPV.
A project costs €400 000 today. It generates €25 000 at the end of the first year, and the cash flow then grows by 3% per year forever. The cost of capital is 10%. Find the net present value NPV.
A project costs €50 000 today. Its cash flow is €5 500 at the end of year 1 and grows by 2% per year until the last cash flow at the end of year 10. The cost of capital is 8%. Find the net present value NPV.
A project costs €100 000 today. Its cash flow is €18 000 at the end of year 1 and grows by 5% per year until the last cash flow at the end of year 5. The cost of capital is 8%. Find the net present value NPV.
Answer key
- 1. PV = 41973 €
- 2. NPV = 34503 €
- 3. NPV = 7988 €
- 4. NPV = −42857 €
- 5. NPV = −10091 €
- 6. NPV = −21169 €
Full step-by-step solutions: practise this topic on examproblems.com.