A project costs €40 000 today and returns €14 500 at the end of each year for 5 years. The required rate of return is 12%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €3 500 at the end of each year for 4 years. The required rate of return is 15%. Find the net present value NPV.
An investment of €30 000 gives these cash flows at the end of years 1 to 4: €9 000, €15 000, €9 000, €11 000. The cost of capital is 8%. Find the net present value NPV.
An investment of €45 000 gives these cash flows at the end of years 1 to 3: €10 000, €12 000, €17 000. The cost of capital is 12%. Find the net present value NPV.
A project costs €40 000 and returns €23 000, €18 500, €25 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €50 000 today. Its cash flow is €9 000 at the end of year 1 and grows by 5% per year until the last cash flow at the end of year 6. The cost of capital is 10%. Find the net present value NPV.
Answer key
- 1. NPV = 12269 €
- 2. NPV = −7.576 €
- 3. NPV = 6423 €
- 4. NPV = −14405 €
- 5. IRR = 30.43 %
- 6. NPV = −6161 €
Full step-by-step solutions: practise this topic on examproblems.com.