A project costs €25 000 today and returns €12 500 at the end of each year for 3 years. The required rate of return is 7.000000000000001%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €12 000 at the end of each year for 5 years. The required rate of return is 8%. Find the net present value NPV.
A project costs €60 000 today and returns €16 000 at the end of each year for 5 years. The cost of capital is 8%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €20 000 gives these cash flows at the end of years 1 to 4: €7 000, €4 000, €9 000, €8 000. The cost of capital is 5%. Find the net present value NPV.
A project costs €10 000 and returns €6 000, €4 000, €4 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Project A costs €20 000 and returns €11 500, €8 000, €4 500 at the end of years 1 to 3. Project B costs €22 000 and returns €6 000, €9 000, €11 500. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. NPV = 7804 €
- 2. NPV = 7913 €
- 3. DPB = 4.643 years
- 4. NPV = 4651 €
- 5. IRR = 20.64 %
- 6. r* = 3.057 %
Full step-by-step solutions: practise this topic on examproblems.com.