A machine is expected to save €10 000, €6 000, €5 000, €10 000 at the end of years 1 to 4, after which it is worthless. The required return is 8%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €100 000 today and returns €24 000, €33 000, €35 000, €24 500 at the end of years 1 to 4. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
A project costs €50 000 today and returns €16 500 at the end of each year for 5 years. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €60 000 gives these cash flows at the end of years 1 to 3: €18 000, €16 000, €17 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €50 000 and returns €20 500, €18 500, €19 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €40 000 and returns €14 500, €14 500, €14 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. PV = 25723 €
- 2. PB = 3.327 years
- 3. DPB = 3.373 years
- 4. NPV = −21072 €
- 5. IRR = 8.36 %
- 6. IRR = 4.314 %
Full step-by-step solutions: practise this topic on examproblems.com.