NPV & IRR worksheet with answers

Free printable NPV & IRR worksheet: 6 problems from easy to exam level, with an answer key. Print it or save it as a PDF.

For teachers: free to print, copy and use in class. Every new worksheet has new values and its own answer key. A link to ExamProblems on your course page is appreciated.

Name: ____________________   Date: ____________

1.Easy
years01234−80 00025 00015 50023 50021 500

A project costs €80 000 today and returns €25 000, €15 500, €23 500, €21 500 at the end of years 1 to 4. Assume cash flows arrive evenly through each year. Find the payback period PB in years.

CF0 = −80 000CF1 = 25 000CF2 = 15 500CF3 = 23 500CF4 = 21 500
PB = years
2.Easy
years0123−25 00010 50010 50010 500

A project costs €25 000 today and returns €10 500 at the end of each year for 3 years. The required rate of return is 5%. Find the net present value NPV.

r = 5%CF0 = −25 000CF1 = 10 500CF2 = 10 500CF3 = 10 500
NPV = €
3.Medium
years0123−30 00014 0008 00014 000

An investment of €30 000 gives these cash flows at the end of years 1 to 3: €14 000, €8 000, €14 000. The cost of capital is 12%. Find the net present value NPV.

r = 12%CF0 = −30 000CF1 = 14 000CF2 = 8 000CF3 = 14 000
NPV = €
4.Medium
years0123…9−400 00047 000+1%+1%…r = 10%, NPV = ?

A project costs €400 000 today. It generates €47 000 at the end of the first year, and the cash flow then grows by 1% per year forever. The cost of capital is 10%. Find the net present value NPV.

C0 = €400 000CF1 = €47 000g = 1%r = 10%
NPV = €
5.Hard
years0123−50 00036 50019 50032 000

A project costs €50 000 and returns €36 500, €19 500, €32 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.

CF0 = −50 000CF1 = 36 500CF2 = 19 500CF3 = 32 000
IRR = %
6.Hard
years0123−20 0009 00011 50013 000

A project costs €20 000 and returns €9 000, €11 500, €13 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.

CF0 = −20 000CF1 = 9 000CF2 = 11 500CF3 = 13 000
IRR = %

Answer key

  1. 1. PB = 3.744 years
  2. 2. NPV = 3594 €
  3. 3. NPV = −1158 €
  4. 4. NPV = 122222 €
  5. 5. IRR = 36.16 %
  6. 6. IRR = 28.81 %