A project costs €25 000 today and returns €10 500 at the end of each year for 4 years. The required rate of return is 5%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €20 000 today and returns €11 000 at the end of each year for 3 years. The required rate of return is 6%. Find the net present value NPV.
A project costs €500 000 today. It generates €32 000 at the end of the first year, and the cash flow then grows by 4% per year forever. The cost of capital is 11%. Find the net present value NPV.
An investment of €20 000 gives these cash flows at the end of years 1 to 4: €7 000, €10 000, €7 000, €7 000. The cost of capital is 10%. Find the net present value NPV.
A project costs €50 000 and returns €24 000, €37 000, €36 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €20 000 and returns €9 000, €11 000, €8 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 12232 €
- 2. NPV = 9403 €
- 3. NPV = −42857 €
- 4. NPV = 4668 €
- 5. IRR = 38.74 %
- 6. IRR = 19.25 %