A project costs €50 000 today and returns €9 500 at the end of each year for 8 years. The required rate of return is 10%. Find the profitability index PI.
NPV & IRR worksheet with answers
A project costs €80 000 today and returns €24 000 at the end of each year for 5 years. The required rate of return is 10%. Find the profitability index PI.
A machine costs €30 000 today. It generates €5 500 at the end of each year for 7 years and can then be sold for €4 500. The cost of capital is 8%. Find the net present value NPV.
A project costs €20 000 today and returns €7 000 at the end of each year for 4 years. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €10 000 and returns €3 500, €4 000, €3 500 at the end of years 1 to 3. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
A project costs €40 000 and returns €15 000, €19 000, €23 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. PI = 1.014
- 2. PI = 1.137
- 3. NPV = 1261 €
- 4. DPB = 3.716 years
- 5. MIRR = 5.977 %
- 6. IRR = 18.95 %