A project costs €10 000 today and returns €5 000 at the end of each year for 3 years. The required rate of return is 6%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €13 000 at the end of each year for 5 years. The required rate of return is 8%. Find the net present value NPV.
An investment of €20 000 gives these cash flows at the end of years 1 to 4: €4 000, €7 000, €9 000, €5 000. The cost of capital is 10%. Find the net present value NPV.
A machine costs €100 000 today. It generates €27 000 at the end of each year for 4 years and can then be sold for €25 000. The cost of capital is 12%. Find the net present value NPV.
An investment of €25 000 returns €6 500 at the end of each year for 5 years. Find its internal rate of return IRR in percent.
Project A costs €10 000 and returns €5 500, €4 000, €2 500 at the end of years 1 to 3. Project B costs €15 000 and returns €4 000, €6 000, €8 000. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. NPV = 3365 €
- 2. NPV = 11905 €
- 3. NPV = −401.6 €
- 4. NPV = −2104 €
- 5. IRR = 9.435 %
- 6. r* = 5.886 %