A project costs €80 000 today and returns €26 500 at the end of each year for 5 years. The required rate of return is 9%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €4 500 at the end of each year for 3 years. The required rate of return is 5%. Find the net present value NPV.
A project costs €100 000 today. It generates €10 000 at the end of the first year, and the cash flow then grows by 2% per year forever. The cost of capital is 11%. Find the net present value NPV.
A machine costs €30 000 today, lasts 9 years and costs €1 000 per year to run (paid at the end of each year). The cost of capital is 5%. Find its equivalent annual cost EAC.
A project costs €40 000 and returns €23 500, €18 500, €23 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €10 000 and returns €5 000, €7 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 23076 €
- 2. NPV = 2255 €
- 3. NPV = 11111 €
- 4. EAC = 5221 €
- 5. IRR = 29.5 %
- 6. IRR = 12.32 %
Full step-by-step solutions: practise this topic on examproblems.com.