A project costs €80 000 today and returns €32 000 at the end of each year for 4 years. The required rate of return is 10%. Find the profitability index PI.
NPV & IRR worksheet with answers
A machine is expected to save €10 000, €6 000, €12 000 at the end of years 1 to 3, after which it is worthless. The required return is 15%. What is the most the company should pay for the machine today? Find PV.
A project costs €30 000 today and returns €7 500 at the end of each year for 5 years. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €30 000 gives these cash flows at the end of years 1 to 3: €12 000, €13 000, €7 000. The cost of capital is 12%. Find the net present value NPV.
A project costs €40 000 and returns €25 500, €17 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
A project costs €200 000 today. Its cash flow is €60 000 at the end of year 1 and grows by 3% per year until the last cash flow at the end of year 4. The cost of capital is 12%. Find the net present value NPV.
Answer key
- 1. PI = 1.268
- 2. PV = 21123 €
- 3. DPB = 4.579 years
- 4. NPV = −3940 €
- 5. IRR = 4.442 %
- 6. NPV = −10187 €