A project costs €80 000 today and returns €21 000 at the end of each year for 5 years. The required rate of return is 6%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €50 000 today and returns €16 500 at the end of each year for 5 years. The required rate of return is 9%. Find the net present value NPV.
A project costs €50 000 today and returns €22 000, €19 000, €15 500, €12 500 at the end of years 1 to 4. The cost of capital is 10%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €30 000 gives these cash flows at the end of years 1 to 3: €6 000, €7 000, €12 000. The cost of capital is 6%. Find the net present value NPV.
A project costs €25 000 and returns €9 000, €11 500, €14 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Project A costs €40 000 and returns €23 000, €15 000, €9 000 at the end of years 1 to 3. Project B costs €45 000 and returns €12 500, €17 500, €24 500. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. NPV = 8460 €
- 2. NPV = 14179 €
- 3. DPB = 3.311 years
- 4. NPV = −8034 €
- 5. IRR = 17.33 %
- 6. r* = 7.076 %
Full step-by-step solutions: practise this topic on examproblems.com.