A project costs €40 000 today and returns €10 500 at the end of each year for 5 years. The required rate of return is 6%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €50 000 today and returns €15 000 at the end of each year for 5 years. The required rate of return is 12%. Find the net present value NPV.
An investment of €60 000 gives these cash flows at the end of years 1 to 4: €21 000, €22 000, €15 000, €24 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €250 000 today. It generates €10 000 at the end of the first year, and the cash flow then grows by 3% per year forever. The cost of capital is 8%. Find the net present value NPV.
A project costs €50 000 and returns €29 500, €18 000, €30 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €25 000 and returns €15 500, €12 000, €9 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 4230 €
- 2. NPV = 4072 €
- 3. NPV = −1519 €
- 4. NPV = −50000 €
- 5. IRR = 25.65 %
- 6. IRR = 24.07 %