A project costs €25 000 today and returns €8 500 at the end of each year for 4 years. The required rate of return is 9%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €60 000 today and returns €15 500, €9 000, €23 000, €23 000, €23 500 at the end of years 1 to 5. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
An investment of €75 000 gives these cash flows at the end of years 1 to 4: €19 000, €24 000, €20 000, €28 000. The cost of capital is 10%. Find the net present value NPV.
An investment of €30 000 gives these cash flows at the end of years 1 to 3: €12 000, €14 000, €7 000. The cost of capital is 9%. Find the net present value NPV.
A project costs €50 000 and returns €26 000, €17 500, €25 000, €20 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
A project costs €200 000 today. Its cash flow is €22 000 at the end of year 1 and grows by 4% per year until the last cash flow at the end of year 10. The cost of capital is 8%. Find the net present value NPV.
Answer key
- 1. NPV = 2538 €
- 2. PB = 3.543 years
- 3. NPV = −3742 €
- 4. NPV = −1802 €
- 5. MIRR = 19.12 %
- 6. NPV = −27102 €