A project costs €20 000 today and returns €9 000 at the end of each year for 3 years. The required rate of return is 7.000000000000001%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €3 500 at the end of each year for 5 years. The required rate of return is 12%. Find the net present value NPV.
A machine costs €20 000 today, lasts 8 years and costs €3 000 per year to run (paid at the end of each year). The cost of capital is 6%. Find its equivalent annual cost EAC.
A machine costs €60 000 today, lasts 7 years and costs €5 000 per year to run (paid at the end of each year). The cost of capital is 6%. Find its equivalent annual cost EAC.
A project costs €40 000 and returns €18 500, €19 500, €24 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €50 000 and returns €19 500, €29 500, €29 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 3619 €
- 2. NPV = 2617 €
- 3. EAC = 6221 €
- 4. EAC = 15748 €
- 5. IRR = 24.72 %
- 6. IRR = 24.48 %
Full step-by-step solutions: practise this topic on examproblems.com.