A project costs €20 000 today and returns €9 000 at the end of each year for 4 years. The required rate of return is 9%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €20 000 today and returns €8 000 at the end of each year for 4 years. The required rate of return is 10%. Find the net present value NPV.
A project costs €60 000 today and returns €24 500, €25 500, €12 000, €14 500, €20 000 at the end of years 1 to 5. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €30 000 gives these cash flows at the end of years 1 to 4: €10 000, €9 000, €8 000, €9 000. The cost of capital is 5%. Find the net present value NPV.
A project costs €10 000 and returns €4 500, €4 500, €6 000, €5 000 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.
A project costs €20 000 and returns €14 500, €11 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 9157 €
- 2. NPV = 5359 €
- 3. DPB = 3.266 years
- 4. NPV = 2002 €
- 5. MIRR = 24.06 %
- 6. IRR = 20.3 %